FBCMUD 122 & 123 - Project Timeline Update: August 2022

August 22, 2022 5:30 pm

The Boards of Fort Bend County Municipal Utility Districts No. 122 and 123 (FBCMUD 122 & 123) know the residents of Lakemont have been eager to hear about the next steps in the process for the park planning following the successful election last year.

Below, we have the updates for both the engineering and park design teams. We have also linked the initial elevation and plan renderings of the facilities.

Engineering

  1. Preliminary Engineering and Schematic Design – Complete
  2. Project Costs and Budget – Complete
  3. Engineering Design of Pond and Site Grading – Early 4th Quarter 2022
  4. Architectural Design Development – 4th Quarter 2022
  5. Engineering Design of Pond and Site Grading Permitting – Late 4th Quarter 2022
  6. Architectural Construction Documents / Permitting – 1st Quarter 2023
  7. Pond and Site Grading Start of Construction – 1st Quarter 2023
  8. Building and Park Start of Construction – 2nd Quarter 2023
  9. Construction Completion – 2nd Quarter 2024

Park Design and Construction

  1. Schematic Design – Complete
  2. Design Development – 4th Quarter 2022
  3. Construction Documents / Permitting – 1st Quarter 2023
  4. Start of Construction – 2nd Quarter 2023
  5. Construction Completion – 2nd Quarter 2024

As the process continues, if residents have any questions regarding the ongoing projects of the Districts, they can reach out via the Contact Us page on the website for their MUD.